Just back from the site visit today and the granite work on the mill building itself is almost complete, just a couple of lintels to be put into place on the back elevation. Nice to see it starting to look like the graphic. Meantime the garage/office is leaping forwards, this is now the ninth week on site and the upstairs space is plaster boarded and plastering commenced today. The views from this space are spectacular, and everyone is really looking forward to seeing the roof go on to the mill, which should commence sometime next week.